Work Inspection Request (WIR): How to Raise One and Pass the First Time
Back to Blog

Work Inspection Request (WIR): How to Raise One and Pass the First Time

Chris AkouryNovember 23, 202610 min read
Document ControlSubmittalsConstruction Correspondence

A work inspection request (WIR) is the contractor's formal notice to the consultant that a piece of work is finished, checked internally, and ready to be inspected before the next activity covers it up or builds on it. It names the activity, the exact location, the approved drawings and the inspection and test plan (ITP) item it covers, and the time the work will be ready. The consultant's inspector checks the work on site and records a result on the same form. Only a passed WIR lets the next activity start.

Most failed WIRs don't fail on the workmanship. They fail because the contractor called the inspector before the work was really ready, attached the wrong drawing revision, or gave a location nobody could find. This guide covers what a work inspection request is, what to attach, how to raise one step by step, a worked example from a Doha project, the mistakes that cost re-inspections, and a checklist you can copy into your own procedure.

What is a work inspection request?

On GCC projects a WIR is also called an inspection request (IR), a request for inspection, or a work inspection notice. They all mean the same thing: a written request, raised by the contractor, for the consultant to inspect completed work at a hold point or witness point before work continues.

It sits next to several documents it is often confused with:

Document Raised by Asks for When
Material approval request (MAR) Contractor Approval of a product before it is ordered Before procurement
Material inspection request (MIR) Contractor Inspection of a delivery against the approved MAR When material reaches site
Work inspection request (WIR) Contractor Inspection of completed work before it is covered or built on When an activity is finished
Request for information (RFI) Contractor An answer to a design question Whenever the design is unclear
Non-conformance report (NCR) Consultant or contractor Correction of work that doesn't meet the specification When a defect is found

The order matters. The MAR approves the product, the MIR confirms the delivery matches it, and the WIR confirms the product was installed as the approved drawings say. The material approval request guide covers the first step.

Where the requirement comes from

Two documents make WIRs compulsory on most GCC projects.

The contract. The FIDIC Construction Contract (2017 Red Book), which most GCC contracts start from, has a sub-clause on inspection (7.3). It requires the contractor to give the Engineer notice whenever work is ready for inspection, before it is covered up or put out of sight. If the contractor doesn't, the Engineer can have the work uncovered and made good at the contractor's cost. Particular Conditions often change the detail, so read your own contract.

The inspection and test plan. The ITP lists every activity that needs checking, who checks it, against which standard, and what evidence is kept. Each line has an intervention point. At a hold point, work must stop until the consultant inspects. At a witness point, the consultant is notified and may attend, and work can continue if they don't. The Designing Buildings wiki has a good overview of ITPs. In practice, every hold point on the ITP becomes a WIR.

The specification then sets the rest: the notice period, the WIR form, the number of copies, and who on the consultant's side may sign the result.

What to include in a work inspection request

Item What it tells the inspector
WIR reference and revision Which request this is, and whether it is a re-inspection
Activity and discipline What they are inspecting, for example "reinforcement, B1 slab, zone 3"
Exact location Building, level, grid lines, zone or chainage, so they can find it
ITP reference Which line of the approved ITP this inspection closes
Drawing numbers and revisions The approved drawings the work was built to
Approved MAR references The materials the work uses, already approved
Contractor's internal inspection checklist, signed That your own engineer checked it first
Supporting records Survey data, test results, calibration certificates, photos of hidden elements
Requested date and time When the work will be ready, within the notice period
Result box for the consultant The decision, comments, name, signature and date

The internal checklist is the item reviewers care about most. A WIR without one tells the inspector they are the first person to look at the work. That is how you get a long list of comments on a slab your own engineer could have fixed the day before.

How to raise a work inspection request, step by step

  1. Check the ITP line. Confirm the activity is a hold or witness point, which inspection it needs, and what records the ITP says to attach.
  2. Check the drawings on site are current. Inspectors check against the latest approved revision. If the gang built from a superseded drawing, you'll find out at the inspection. The drawing revision control guide covers how to keep old sheets off site.
  3. Inspect it yourself first. Your site engineer walks the work with the ITP checklist and fixes what they find. Sign the checklist only when the work is actually ready.
  4. Fill in the WIR form. Use the project's numbering, give the exact location, and list the drawings with their revisions. One activity in one location per WIR.
  5. Attach the records. The signed internal checklist, plus any survey, test results or photos the ITP asks for.
  6. Submit it within the notice period. The specification sets how much notice the consultant gets. Send it through the project's document control route, on a transmittal or the agreed system, not by text message.
  7. Log it. Record the WIR number, activity, location, requested time and status in the WIR log the day it goes out.
  8. Attend the inspection. The engineer who signed the internal checklist walks the inspector through the work, with the drawings.
  9. Record the result on the form. The inspector writes the result and comments and signs. Don't leave site with a verbal "it's fine".
  10. Act on the result. Passed means the next activity can start. Comments get closed before it does. A rejection means fix, re-inspect internally, and raise the next revision of the same WIR.

What the inspection result means

Projects use their own result codes, defined in the specification. Most schemes come down to three outcomes:

Result Can the next activity start? What the contractor does
Approved Yes File the signed WIR and start the next activity
Approved with comments Yes, once the comments are closed Close the comments, record how, then proceed
Rejected, re-inspection required No Fix the work, re-inspect internally, submit the next revision

Some projects add a fourth result for "not ready", when the inspector arrives and the work isn't complete. Treat it as a rejection in your log, because that's what it costs you. A serious or repeated defect often comes with an NCR, which has its own close-out route.

The logic is the same as submittal codes, but the stakes are different. A rejected shop drawing delays an order. A rejected WIR stops a crew. The approval codes guide explains how codes work on the submittal side.

A worked example

A contractor on a mid-rise residential project in Doha is ready to pour the basement B1 slab, zone 3. The ITP lists reinforcement inspection as a hold point, and the specification asks for a set notice period before each inspection.

WIR-STR-0142 revision 0 goes in at the end of the day for an inspection the next morning. It gives the location as "B1 slab", lists the structural drawings without their revisions, and has no internal checklist attached. The inspector arrives, spends twenty minutes finding zone 3, and finds missing cover spacers along one edge and bars lapped short at two locations. The result is rejected, re-inspection required. The concrete order for the afternoon gets cancelled.

Revision 1 goes in that afternoon. The site engineer has walked the zone with the ITP checklist and fixed the spacers and laps. The WIR now reads "B1 slab, zone 3, grids C to F / 4 to 7", lists each drawing with its current revision, and attaches the signed checklist and photos of the corrected laps. The inspector passes it the next morning with one comment, to clean the formwork before the pour. The engineer clears it before the pump arrives.

The rebar defects were small and quick to fix. What cost the day was raising the WIR before anyone had checked the work: a cancelled pour, a crew standing, and a slab activity a day late.

Keep a WIR log

Every WIR goes in a log, the same way every submittal goes in the master document register. At minimum, track:

  • WIR number and revision
  • Activity, discipline and exact location
  • ITP reference
  • Date submitted and requested inspection time
  • Result, with the date it was given
  • Open comments, and the date each was closed
  • Linked NCR, if any

The log answers the questions the project manager and the client ask: which inspections are pending, which failed and why, and which areas are cleared for the next activity. It also feeds the handover file. The signed WIRs for hidden work, such as reinforcement, buried services and waterproofing, are often the only proof of what is inside the building.

Common mistakes with work inspection requests

  • Calling the inspector before the work is ready. It wastes the inspector's time and your credibility on every WIR that follows.
  • Vague locations. "Ground floor" is not a location. Give the grid lines or the zone.
  • No drawing revisions. If the WIR doesn't say which revision, nobody can prove what the work was built to.
  • Too much in one WIR. A WIR covering a whole floor fails on its worst corner. Split it by zone or pour.
  • Verbal approvals. "Go ahead, I'll sign later" is how covered work ends up with no signed record.
  • Covering work without a result. If the work was covered without notice, FIDIC-based contracts make the contractor pay to open it up again when the Engineer asks.
  • New numbers for re-inspections. Raise the next revision of the same WIR, so the history stays on one record.

Tracking work inspection requests in Mowafeq

In Mowafeq, a project can set up the WIR as its own document type, with custom fields for the location, the activity and the ITP reference, and automatic reference numbers in the project's format. The WIR goes to the consultant on a transmittal, and the result comes back on the same record, using the response statuses the project defines. The inspector can respond to transmittals from the Mowafeq mobile app on site, in English or Arabic. Saved Views such as Awaiting our response and Overdue show which WIRs are still open, and the registry exports to Excel when the client asks for the log. Contractors can see how this works on the contractor page, and consultants on the consultant page.

Checklist: before you send a WIR

  • The activity is on the approved ITP, and you know whether it is a hold or witness point.
  • The drawings on site are the current approved revisions.
  • Your site engineer has inspected the work and signed the internal checklist.
  • The form has the WIR reference, revision, activity, exact location and ITP reference.
  • Every drawing is listed with its revision, and the materials have approved MARs.
  • Survey data, test results and photos the ITP asks for are attached.
  • It goes in within the notice period, through the project's document control route.
  • It is in the WIR log with its requested inspection time.
  • The engineer who checked the work will attend the inspection.

Frequently asked questions

Who raises a work inspection request?

The contractor, usually the site or QA/QC engineer responsible for the activity. Subcontractors normally raise WIRs through the main contractor, who checks them first, because the main contractor holds the contract with the client.

How much notice does the consultant need for a WIR?

Whatever the specification or the approved quality plan says. Check it at the start of the project and build it into your look-ahead program, so WIRs go in early enough for the pour or the next trade.

What happens if the inspector doesn't attend?

Check the contract and the specification. Some let the contractor proceed at a witness point, or after a stated period without a response. At a hold point, don't cover the work until you have the result or a written instruction to proceed, and record the missed inspection in writing.

What is the difference between a WIR and an MIR?

A material inspection request (MIR) asks the consultant to inspect materials when they are delivered to site. A work inspection request asks them to inspect the work after the materials are installed.

Does a rejected WIR need a new number?

On most projects, no. Raise the next revision of the same WIR, so the rejection and the re-inspection sit on one record. Some specifications ask for a new number, so follow yours.

Explore Mowafeq document control features