Shop Drawing Review: How Consultants Check, Comment and Return Them on Time
Shop drawing review is the consultant's check that a contractor's shop drawings follow the design intent and the contract documents before anything is fabricated or installed. A good review does five things: it logs the received date, screens the package for completeness, routes it to every discipline that needs to see it at the same time, records clear and numbered comments, and returns one coded response inside the contract's review period.
Most late shop drawing reviews are not late because the engineering is hard. They are late because the drawing waited in an inbox, went from one discipline to the next in sequence, or came back with comments the contractor couldn't act on, so the same sheet went round twice more. This guide covers what a shop drawing review should and shouldn't cover, who does what, a step-by-step process with internal deadlines, how to write comments that close, a worked example, and a checklist you can copy into your own procedure.
What a shop drawing review covers, and what it doesn't
Shop drawings develop the design team's drawings into the detail a fabricator or installer needs. The Designing Buildings wiki describes them as showing how a component "will actually be manufactured, fabricated, assembled or installed", prepared by contractors, subcontractors, suppliers and fabricators, and reviewed by the design team.
The consultant reviews for general conformance: does this drawing deliver what the design and the specification ask for, and does it fit with the other packages around it? The contractor keeps responsibility for quantities, dimensions, site conditions, fabrication methods and coordination between its own trades. A US federal guidance note from the NIH on review versus approval of construction submittals puts the order clearly: the contractor reviews first, as part of its own quality control, then the designer of record checks conformance with the contract documents.
The same split appears in the contracts most GCC projects start from. FIDIC's 2017 Red Book says that an approval, check or Notice of No-objection from the Engineer does not relieve the contractor of its own obligations. Check that your Particular Conditions keep this, and make your stamp wording say the same thing, in plain words, on every returned sheet.
Two things a shop drawing review is not:
- A redesign. If the reviewer wants something the contract documents don't require, that is a change, and it belongs in an instruction or variation, not in a review comment.
- A material approval. The drawing shows how something is built. The product itself is approved through a material approval request. A shop drawing that relies on an unapproved product should say so, and the reviewer should flag it.
Who reviews a shop drawing
Every shop drawing has a lead discipline that owns the response, and often one or more supporting disciplines that check the interfaces. The document controller logs and routes it, and a named person, usually the discipline lead or the project manager, signs the response.
| Shop drawing | Lead reviewer | Also check |
|---|---|---|
| Reinforcement and formwork | Structural | Architectural for openings and finishes |
| Curtain wall and facade | Architectural | Structural for brackets and loads |
| Ductwork and chilled water layouts | Mechanical | Electrical, fire, architectural ceiling heights |
| Cable trays and containment | Electrical | Mechanical for clashes in shared zones |
| Fire alarm and sprinkler layouts | Fire or MEP | Architectural, and the authority's requirements |
| Joinery and fit-out details | Interior or architectural | MEP for fixtures and outlets |
Agree this matrix at the start of the project and put it in the document control procedure. If routing depends on memory, supporting disciplines get skipped and the clash shows up on site.
The shop drawing review process, step by step
The steps below assume a review period of 14 calendar days. Use the number in your own contract. The submittal review period guide explains how to count it and what a resubmission does to the clock.
- Log it on receipt (day 0). Record the transmittal number, drawing numbers, revisions and the received date. The received date starts the contract clock, so it is the most important field in the register.
- Screen it within one working day. Check the package before an engineer spends time on it: correct project and drawing numbers, revision letters, the contractor's own review stamp, a title block, references to the design drawings it develops, and revision clouds on any resubmitted sheet. An incomplete package goes back at once, with a short list of what is missing.
- Route to all disciplines at once. Send it to the lead and supporting reviewers in parallel, not one after the other. Sequential routing is the single biggest cause of late reviews.
- Set internal due dates inside the review period. For a 14-day period: discipline reviewers by day 8, the lead consolidates by day 11, the signatory signs by day 12, and the document controller issues by day 13. A buffer day is not slack. It is what absorbs a reviewer's leave.
- Review against the contract documents and a checklist. Use the checklist below so two engineers reviewing the same kind of drawing check the same things.
- Mark up the drawing and write numbered comments. Each comment points to the sheet and grid line, says what doesn't conform, and cites the drawing or specification clause it comes from.
- Consolidate into one response. The lead discipline removes duplicates, resolves comments that contradict each other, and decides the code. The contractor should never receive two answers to one drawing.
- Assign the code and stamp the drawing. Use the codes and stamp legend your specification defines. The approval codes guide explains what Code A, B, C and D usually mean.
- Return it on a transmittal and log the response date. The response date closes the review clock and, for a Code C, starts the contractor's resubmission clock.
- On a resubmission, check the old comments first. Review only the clouded changes and the response to each previous comment. If the contractor has changed things outside the clouds without saying so, that is a comment in itself.
What to check on a shop drawing
| Area | What the reviewer checks |
|---|---|
| Package | Drawing numbers, revisions, title block, contractor's review stamp, references to design drawings |
| Design intent | Layout, sizes, routes and details match the design drawings and specification |
| Dimensions and levels | Critical dimensions, setting-out and levels against the design; clearances shown |
| Materials and products | Products shown match approved material submittals; unapproved ones flagged |
| Interfaces | Connections to other packages, openings, penetrations, ceiling zones and access for maintenance |
| Deviations | Every departure from the design is declared, with a reason, not hidden in a detail |
| Codes and authorities | Items needing authority approval, such as fire and life safety, are identified |
| Revisions | Changes since the last revision are clouded and listed in the revision block |
If the shop drawing is based on a superseded design revision, stop the review and say so in the first comment. Everything else depends on it. The drawing revision control guide covers how to keep superseded drawings out of circulation.
How to write review comments that close
A comment is only useful if the contractor can act on it without a meeting. Compare these:
| Weak comment | Comment that closes |
|---|---|
| "Check duct sizes." | "Sheet M-302, grid C/4: supply duct shown 600 x 400. Design drawing M-102 Rev C shows 800 x 400. Revise to suit." |
| "Coordinate with structure." | "Sheet M-303, grid D/2: duct crosses beam B-12 at 2,950 mm. Beam soffit is 3,000 mm. Show the clearance or reroute." |
| "Not acceptable." | "Sheet M-305: access panel for the fire damper is not shown. Specification 23 33 00, 3.2 B requires one. Add it." |
Four rules make the difference:
- One issue per comment, numbered. The contractor responds comment by comment, and the next review checks them one by one.
- Point to the source. A drawing number and revision, or a specification clause. A comment without a source reads as an opinion.
- Separate mandatory from advisory. Mark comments that are suggestions as such, or the contractor will treat everything as a condition of approval.
- Don't add requirements. If the contract doesn't require it, it isn't a review comment.
A worked example
A consultant on a mid-rise office building in Lusail receives a transmittal from the MEP contractor: six sheets of ductwork and chilled water layouts for one typical floor. The specification sets a 14-day review period.
The document controller logs it the same morning and screens it. One sheet references an old revision of the mechanical design, so the screening note asks the contractor to confirm the base revision, while the review goes ahead on the other five. The package goes to mechanical as lead, with electrical and architectural as supporting reviewers, all on the same day.
Architectural finds that two duct runs leave less than the ceiling zone shown on the reflected ceiling plan. Electrical finds a cable tray clash in the corridor. Mechanical finds the access panel issue and one undersized branch. By day 9, the lead mechanical engineer has seven comments from three disciplines, removes one duplicate, and returns six numbered comments with a Code C on day 11.
The contractor resubmits nine days later with the clouded changes and a response to each comment. The second review checks six responses and the clouds only, and comes back as Code A in six days. On a sequential route, the same first review would have reached the third discipline around day 12, and one of the clashes would likely have been found in the second round instead of the first.
Why shop drawing reviews run late
The causes repeat from project to project. The drawing arrives by email and waits days before a reviewer knows it exists. Disciplines review one after the other. Nobody can see the queue, so the project manager learns a review is late when the contractor complains. And every vague comment adds a cycle.
The fix is mostly process, but the record matters too. In a published case study, the same Doha consultancy ran submittals on two projects, one on its legacy email-and-spreadsheet process and one on Mowafeq. Shop drawings came back in a median of 20 days on the legacy project and 6 days on Mowafeq, and the share returned within 14 days went from 40% to 82%.
Common mistakes in shop drawing review
- Starting the review before screening. An engineer spends a day on a package that is missing half its sheets.
- Taking over the contractor's responsibility. Writing "dimensions checked and correct" on a stamp moves risk to the consultant.
- Two responses to one drawing. Disciplines reply separately, and the contractor builds to the one it prefers.
- Approving a drawing that relies on an unapproved material. The drawing gets ahead of the material submittal.
Running shop drawing reviews in Mowafeq
In Mowafeq, the contractor sends each shop drawing on a transmittal, so it reaches the consultant with the date recorded by the system. The document controller can split one transmittal into several review workflows, one per discipline, so structural, MEP and architectural review in parallel, and the Workflows page shows each reviewer what is waiting on them. Reviewers mark up and stamp the PDF in the browser, Send response from all files returns one consolidated response, and Workflow Analytics shows which step is holding reviews up. Consultants can see how it fits their review desk on the consultant page.
Checklist: shop drawing review
- The review matrix (lead and supporting disciplines per drawing type) is in the document control procedure.
- The received date is logged on the day the transmittal arrives.
- The package is screened within one working day, and incomplete packages are returned at once.
- All disciplines receive the drawing at the same time.
- Internal due dates are set inside the contract review period, with a buffer.
- The base design revision is confirmed before the review starts.
- Comments are numbered, cite a source, and separate mandatory from advisory.
- No comment adds a requirement the contract doesn't contain.
- One consolidated response goes back, with one code per drawing.
- The stamp wording says the review does not relieve the contractor of its obligations.
- On resubmission, every previous comment is checked before anything else.
Frequently asked questions
What is the difference between reviewing and approving a shop drawing?
Most consultants review for general conformance with the design and the contract documents, and their stamp says so. The contractor remains responsible for dimensions, quantities, fabrication and coordination. "Approved" on a stamp does not usually transfer that responsibility, and under FIDIC-based contracts an Engineer's no-objection doesn't relieve the contractor of its obligations.
How long does a shop drawing review take?
As long as the contract allows, at most. FIDIC 2017 design-build conditions default to 21 days, and many GCC specifications set their own period. Plan internal due dates so the response goes out a day or two early.
Who signs a shop drawing review?
Whoever your procedure names, usually the lead discipline engineer or the consultant's project manager, and on some projects the resident engineer. Decide it at the start of the project and keep it consistent.
Can a consultant add requirements in shop drawing comments?
No. If the requirement isn't in the contract documents, it is a change and needs an instruction. A review comment that adds scope invites a variation claim.