Material Approval Request (MAR): What to Include and How to Get It Approved
A material approval request (MAR) is the contractor's formal request to the consultant to approve a specific product, from a named manufacturer and supplier, before it is ordered or installed. It carries a cover form, a statement of compliance against the specification, the technical data sheets, test certificates, and samples where the specification asks for them. The consultant returns it with an approval code, and only an approved MAR lets the contractor place the order with confidence.
Most rejected MARs are not rejected because the product is wrong. They are rejected because the package doesn't prove the product is right. The reviewer can't find the selected model in a 40-page catalog, a certificate has expired, or a deviation from the specification is buried instead of declared. This guide covers what goes into a material approval request, how to build and submit one step by step, a worked example from a GCC project, and a checklist you can copy into your own procedure.
What is a material approval request?
On GCC projects the terms "material approval request", "material submittal" and "material submission" usually mean the same thing: a submittal that asks the consultant to accept a material before it is used in the works. In US-style specifications the same package is often called "product data" plus "samples". The Designing Buildings wiki gives a short overview of construction submittals and their types.
The contract usually backs it. The FIDIC Red Book includes a sub-clause on samples (7.2) in its clause on plant, materials and workmanship, under which the contractor submits samples of materials, with relevant information, to the Engineer before using those materials in the works. Your project's specification then sets out the detail: what each MAR must contain, how many copies, and how long the review takes. The FIDIC Construction Contract (2017 Red Book) is the general form most GCC contracts start from, and the Particular Conditions often change it.
A MAR is not the same as three documents it is often confused with:
- Shop drawing. Shows how the contractor will build or install something. A MAR shows what product they will use.
- Material inspection request (MIR). Asks the consultant to inspect a delivery when it reaches site, to check it matches the approved MAR. No approved MAR, no meaningful MIR.
- Request for information (RFI). Asks a question about the design. If the specification is unclear about a product, raise the RFI first, then submit the MAR. The RFI guide covers that process.
What to include in a material approval request
The specification's submittal section is the authority. Read it first. Most GCC specifications ask for some version of the list below.
| Item | What it proves to the reviewer |
|---|---|
| Cover form | Which project, which specification section, which product, which revision |
| Compliance statement | That the product meets each requirement, clause by clause |
| Technical data sheet, with the selected product marked | The exact model, size, grade or color you will supply |
| Test reports and certificates | That the performance claims were tested, and the certificates are current |
| Manufacturer and supplier details | Who makes it, who supplies it, the country of origin |
| Authority approval, where required | That a local authority accepts the product, for example a fire-rated item |
| Samples or a sample board | What the reviewer is approving, physically, where the specification asks for it |
| Warranty | That the warranty matches the period the specification requires |
| Installation instructions | How the manufacturer says the product must be installed |
The cover form normally carries the MAR reference and revision, the date, the discipline, the specification section and clause, the material description, the trade name, the manufacturer, the supplier, the country of origin, and the location in the works where it will be used. Leave a box for the consultant's approval code and comments.
The compliance statement decides the review
The compliance statement is the page most contractors skip and most reviewers read first. It is a table that takes every requirement in the specification section and states, for each one, whether the proposed product complies, and where the proof is.
| Spec clause | Requirement | Proposed product | Status | Evidence |
|---|---|---|---|---|
| 2.1 A | Minimum thickness as specified | Meets it | Complies | Data sheet p. 2, highlighted |
| 2.1 C | Tested to the standard named in the specification | Tested | Complies | Test report, appendix B |
| 2.3 | Warranty period as specified | Shorter by two years | Deviates | Manufacturer's warranty letter |
A good compliance statement does three things. It answers every clause, not only the ones the product meets. It points to the exact page of evidence. And it declares deviations openly, with a reason and, where possible, an offer such as an extended supplier warranty. A reviewer who finds an undeclared deviation stops trusting the rest of the package. A reviewer who sees it declared can approve with comments.
How to submit a material approval request, step by step
- Read the specification section in full. Note the performance requirements, any named manufacturers, the "or equal" wording, and the submittal requirements for that section.
- Check that the product is acceptable in principle. If the specification names manufacturers and yours is not one of them, you are proposing a substitution. Say so on the cover form, not in a footnote.
- Collect current documents from the supplier. Ask for the latest data sheet, test reports and certificates for the exact product, not the product family. Check the expiry date on every certificate.
- Mark up the data sheet. Highlight the selected model, size, grade and finish, and cross out what doesn't apply.
- Write the compliance statement, clause by clause, with page references.
- Run an internal review before it leaves your office. The QA/QC engineer checks compliance and the project manager checks cost and lead time. The internal review guide shows how to set one up.
- Number it and send it on a transmittal for approval. One product, or one closely related system, per MAR. The transmittal guide explains purposes of issue.
- Log the due date. The review period comes from the contract. The submittal review period guide explains how to count it.
- Act on the response. Approved, or approved with comments, means procurement can go ahead, with the comments passed to the buyer and the supplier. Revise and resubmit means a new revision, with a response to every comment. The approval codes guide explains each code.
- Keep the approved MAR and its sample where site can find them. The inspector will check deliveries against them, and the approved MAR goes into the O&M manual at the end. The handover documents guide covers that package.
A worked example
A contractor on a mid-rise residential project in Doha needs a waterproofing membrane for the basement. The specification names the performance requirements, the test standard and a warranty period, and asks for a sample.
Revision 0 goes in with the manufacturer's full product catalog, a test certificate, and the sample. The consultant returns it as revise and resubmit, with three comments: the catalog covers four membranes and none is marked; the test certificate expired last year; and the warranty in the catalog is shorter than the specification requires, with no mention of it in the submission.
Revision 1 goes in two weeks later. It has a cover form, a compliance statement with the warranty shortfall declared and a supplier letter extending it, the data sheet for one membrane with the thickness highlighted, and a current certificate. The consultant approves it with one comment: submit the manufacturer's installation method statement before work starts.
The product never changed between the two revisions. Only the evidence did. The two weeks lost on revision 0 came out of the procurement lead time, which on an imported product can be the difference between the membrane arriving before the excavation is ready or after.
Common mistakes with material approval requests
- Sending the whole catalog. The reviewer has to guess which product you mean, so they send it back.
- Expired or generic certificates. A certificate for the product family, or one that expired before submission, doesn't prove anything about what you will deliver.
- Hiding a substitution. Proposing a different manufacturer from the one named in the specification, without saying so, is the fastest way to lose the consultant's trust.
- Bundling unrelated products. A MAR with tiles, adhesive, grout and a waterproofing membrane gets held up by the slowest item. Split it.
- Ordering before approval. It happens under program pressure, and it leaves the contractor carrying the cost when the MAR comes back rejected.
- Losing the comments. An approval with comments is only useful if the comments reach the supplier before the order is placed.
- No link to the sample. If the approved sample isn't labeled with the MAR reference and kept on site, the inspector has nothing to compare the delivery against.
Tracking material approval requests in Mowafeq
In Mowafeq, a project can set up a material approval request as its own document type, with custom fields for details such as the specification section or the manufacturer, and automatic reference numbers that follow the project's format. The MAR goes to the consultant on a transmittal, and the response comes back on the same record with its status. On the consultant's side, reviewers mark up and stamp the PDF in the browser, and a document controller can split one transmittal into several review workflows when a material needs both architectural and MEP review. Saved Views such as Awaiting our response and Overdue show which MARs are still open. And because Mowafeq AI answers with page-level citations from the project's documents, anyone with Mowafeq AI can ask which membrane was approved for the basement and open the approved copy from the answer. Contractors can see how this works on the contractor page, and consultants on the consultant page.
Checklist: before you send a MAR
- The specification section, submittal requirements and any named manufacturers have been read in full.
- Any substitution is declared on the cover form.
- The cover form shows the MAR reference, revision, specification section, product, manufacturer, supplier and country of origin.
- The compliance statement answers every clause, with page references and any deviations declared.
- The data sheet is for one product, with the selected option highlighted.
- Every test report and certificate is current and for the exact product.
- Authority approvals are included where the specification or authority requires them.
- The sample is labeled with the MAR reference, if the specification asks for one.
- QA/QC and the project manager have reviewed it internally.
- It goes on a transmittal for approval, and the due date is in the register.
Frequently asked questions
Is a material approval request the same as a material submittal?
On most GCC projects, yes. "Material approval request", "MAR", "material submittal" and "material submission" all describe the package that asks the consultant to approve a product before it is used. Use whatever term your specification uses.
What is the difference between a MAR and an MIR?
A MAR asks the consultant to approve a product before it is ordered. A material inspection request (MIR) asks the consultant to inspect the delivered material on site, to confirm it matches the approved MAR.
Can the contractor order materials before the MAR is approved?
Whatever the contract says about it, the risk sits with the contractor. If the MAR comes back rejected, the material may have to be returned or replaced at the contractor's cost. For long-lead items, submit early instead of ordering early.
What if the specified product is no longer available?
Raise it early, in writing, and submit a MAR for the proposed alternative as a substitution, with a compliance statement against the original specification. Some contracts treat a substitution as a variation, so check the contract before you assume it is a like-for-like swap.
How long does the consultant have to review a MAR?
The review period in your contract or specification. It is the same clock that applies to other submittals, and a resubmission usually starts a new period.